Road Construction


Draper City works diligently to maintain and repair all roads within city limits in a timely manner. Detailed overviews of road projects taking place throughout the city can be found here. The city's interactive map, which can be accessed below, details current road projects and their locations. Projects can be filtered by address with the "Search" widget.

Single Event Lic Button Opens in new window

Please note that project start and end dates are subject to change. If you have questions on these projects, contact Draper City's Engineering office by email, or phone at (801) 576-6585.


Project Spotlights

Traverse Ridge Road Water Line Improvement
TimelineDecember 5 - 23
Project BackgroundStarting Monday, December 5, the outside lane traveling uphill toward SunCrest on Traverse Ridge Rd will be closed, related to work on the water line improvement project. Beginning Monday, December 12 the inside lane traveling uphill will also close and traffic will shift to one lane each direction on the downhill side. This traffic pattern is expected to be in place until approximately December 23. 
Updates


1300 East Widening
TimelineAugust 8 through late November
Project Background1300 East will be widened from Highland Dr to Nashi Lane. New traffic signals will be added at Wayne's World Dr and Highland Dr.
UpdatesThe week of December 5 - 10, crews will finish prep and begin placement of concrete sidewalk and driveways.

The week of November 28 - December 4, the east side of 1300 East will see preparation from asphalt driveway transitions, and asphalt driveways will be paved on Thursday. Crews will resume prep for concrete sidewalk and driveways for the remainder of the week.

The week of November 21 - 27, the east side of 1300 East will experience removals, excavation, prep for sidewalks and driveways, curb and gutter placement, sidewalk and driveways placement, irrigation systems, and asphalt paving on Wednesday.

The week of November 14 - 20, the east side of 1300 East will experience removals, excavation, irrigation systems, and curb and gutter placement Thursday and Friday, and prep for sidewalk and driveways on Saturday.

The week of November 7 - 12, the east side of 1300 East will experience clearing of grub, removals, excavation, and storm drain installation. Highland Drive will experience microsurfacing and striping.

The week of October 31 - November 5, the east side of 1300 East will experience clearing of grub, removals, excavation, and storm drain installation. Highland Drive will experience asphalt paving in the northeast corner.

The week of October 23 - 30, the east side of 1300 East will experience clearing of grub, removals, excavation, and storm drain installation. Highland Drive will experience curb and gutter work, median curb installation, landscaping, and signage installation.

The traffic lane switch on 1300 East from the east to the west side is planned for October 14. Additional planned work includes grading, sidewalk/driveway pouring, and traffic signal work on the west side, and clearing grub, removals, and excavation on the east side. Tree removals on the east side of 1300 East will be performed by Diamond Tree on October 18 - 20. Additional work includes clearing grub, removals, excavation, grading, granular borrow and road base, and storm drain installation.

On Monday, August 8, Geneva Rock will start working on the west side of the street, from Highland Dr to Nashi Lane. Travel lanes will be shifted to the east side of 1300 East. Consequently, right turns from Wayne’s World Drive onto 1300 East will be prohibited and right turns onto Highland Drive will be Stop-controlled during this initial phase of construction.

Trail Impacts:
The parking area by the South Mountain Bridge will be closed until December. Please use another parking area to access the Porter Rockwell Trail, such as Draper Park, Sadler Trailhead, or Osbourne Trailhead. 

The Draper Canal Trail crossing at 1300 E will be closed from August 12 through late November.

The Porter Rockwell Trail crossing at 1300 E will have intermittent closures beginning in late August.


1300 East and Pioneer Rd. Roundabout
TimelinePostponed until 2023
Project BackgroundTo improve traffic flow, a second lane will be added through the roundabout in the NB and SB directions on 1300 E. New dedicated right turn lanes will be added on the EB and WB approaches of Pioneer Rd.
Updates


UDOT Projects

Draper City does not have control over UDOT (state transportation) projects. UDOT projects in Draper will be posted below as they occur, with links to UDOT's website for more information.